Components – Five Functional Systems

Five Systems Inside Every Substation — Package Substation
Components

Five Systems Inside Every Substation

High-voltage receiving, transformation, low-voltage distribution, enclosure and auxiliary systems — the five functional blocks a BOM is built from.

HV incomingTransformerLV boardEnclosure & aux

Read the substation as five systems

A package substation is not a single product; it is five systems that have to fit one enclosure. Splitting it this way is how we size a BOM — each system maps to a group in the BOM library.

High-voltage switchgear cabinet — Package Substation

HV System

High-voltage incoming and distribution: ring main units / MV switchgear, load switches, vacuum circuit breakers, HV fuses, surge arresters, CT, PT, live indicators and distribution automation terminals (FTU/DTU).

Read more →
Dry-type transformer — Package Substation

Transformer System

The core power-transforming unit of the package substation: a dry-type (SCB), oil-immersed (S11/S13) or amorphous-alloy (SH15) transformer, supplied complete with temperature controller and cooling fans (dry-type) or Buchholz relay and oil-level gauge (oil-immersed). Typical capacity 315-1250 kVA.

Read more →
LV switchboard assembly — Package Substation

LV / Distribution System

Low-voltage switchgear and outgoing feeder circuits: LV switchboard (GGD/GCS/MNS), ACB (CW1), MCCB (CM1), disconnectors, ATS, LV CT, multifunction meter and SPD, plus the capacitor compensation cabinet for reactive-power correction.

Read more →
Outdoor box substation enclosure — Package Substation

Enclosure & Structure

Factory-built enclosure that houses the HV, transformer and LV compartments: steel / stainless-steel / GRC cabinet with thermal insulation, ventilation louvers, moisture-proofing, base frame and cable basement. Delivered complete as one assembly.

Read more →
Control and metering cabinet — Package Substation

Auxiliary Systems

Supporting systems inside the enclosure: anti-condensation heaters and temperature/humidity controllers, interior lighting and maintenance sockets, ventilation fans / air conditioning, fire suppression, grounding and security monitoring. Mostly standard industrial fittings specified per project.

Read more →

The five images on this page are product photographs of the equipment represented by each system; model numbers and ratings are still confirmed against the single-line diagram.

The five systems, side by side

ParameterTypical value
HV systemRMU / withdrawable switchgear, load switch, VCB, fuse, arrester, CT/PT, FTU/DTU
TransformerDry-type SCB, oil-immersed S11/S13 or amorphous SH15; 100–1600 kVA
LV systemGGD / GCS / MNS board, ACB, MCCB, ATS, LV CT, meter, SPD, compensation
EnclosureSteel / stainless / GRC cabin, three compartments, insulation, louvers, base frame
AuxiliaryHeater + controller, ventilation or A/C, lighting, sockets, fire suppression, earthing

One row per system is how the BOM is checked line by line; the BOM library holds the item-level detail behind each row.

Why the split matters at enquiry stage

Most scope mistakes happen at the boundary between systems: the CT ratio that does not match the meter, a protection degree that only covers the enclosure, or an LV board ordered without the cable-termination space it needs. Reading the five systems together is the cheapest way to avoid it.

Frequently asked questions

QWhat are the five systems in a package substation?
A

High-voltage receiving, the transformer, low-voltage distribution, the enclosure and structure, and the auxiliary systems. Every item in the BOM Library belongs to one of these five groups.

QWhy split a substation into five systems?
A

Because scope errors happen at the boundaries — a CT ratio that does not match the meter, or an LV board ordered without cable-termination space. Splitting the systems makes those boundaries visible before the order.

Package Substation

Specialized in package substations, switchgear cabinets and distribution components for global B2B projects. Configuration and bill of materials are fixed against the single-line diagram; assembly, wiring and routine test follow that drawing.

6 / 10 / 35 kV · 100–3150 kVA · IP54+

© 2026 Package Substation. All rights reserved.PrivacyContactmanager@packagesubstation.com
Scroll to Top